Zim gets US$310m for Hwange power upgrades

Hwange Unit 7 testing in final stages

3 years ago
China in Africa: Who is fooling who?

China in Africa: Who is fooling who?

1 year ago
Sino-Zim: Turning the ironclad pact into dollars

Sino-Zim: Turning the ironclad pact into dollars

1 year ago
If our friends in China did it…

If our friends in China did it…

1 year ago
Handbook to guide Gukurahundi Outreach

Handbook to guide Gukurahundi Outreach

2 years ago
Harare building collapses, woman dies

Harare building collapses, woman dies

2 years ago
Africa backs Zimbabwe’s Security Council bid

Africa backs Zimbabwe’s Security Council bid

2 years ago
ED says no to third term

ED says no to third term

2 years ago
Banks start changing accounts to ZiG

Banks start changing accounts to ZiG

2 years ago
SADC will prioritise food security, says Incoming Chairperson

SADC will prioritise food security, says Incoming Chairperson

2 years ago
Caps fans invade pitch, match abandoned

Caps fans invade pitch, match abandoned

2 years ago
Measures to promote use of ZiG

Measures to promote use of ZiG

2 years ago
ZiG starts circulating on April 30

ZiG starts circulating on April 30

2 years ago
  • About
  • Advertise
  • Privacy & Policy
  • Contact
Monday, December 1, 2025
  • Login
Zim Sentry
  • Local News
  • Africa
  • International
  • Thought Leader
  • Economy
  • Lifestyle
  • SportsTrending
No Result
View All Result
Zim Sentry
No Result
View All Result
Home Local News

Hwange Unit 7 testing in final stages

January 5, 2023
in Local News
0
Zim gets US$310m for Hwange power upgrades
492
SHARES
1.4k
VIEWS
Share on FacebookShare on Twitter

THE commissioning of Unit 7 at the Hwange Thermal Power Plant is “almost complete,” with engineers now finalising works on the protection system that allows evacuation of power to the grid, Energy and Power Development Minister, Zhemu Soda, said yesterday.

Commercial production was initially expected to start at the end of December 2022.

But there were challenges in mobilising technicians from the Chinese company, ABB, to conduct the testing on the evacuation protection system following the resurgence of Covid -19 in the Asian country.

“The testing of the power plant was done and passed,” said Minister Soda in an interview. “We are only left with the testing of the protection system that allows for the evacuation of power to the transmission system and a team from China only came into the country during mid-December when we initially expected them in November.

“There was also a delay in them understanding all the systems; we are now expecting them to complete the test in three weeks and to have the plant run by end of this month.”

Unit seven will produce 300MW and unit eight, to be commissioned later in this quarter will also have the same capacity.

“We don’t expect to take much longer to commission unit eight because we have learnt many lessons from the current unit,” said the Minister.

After the commissioning of the Hwange 7 & 8, Zesa intends to start major rehabilitation of the existing units to restore their capacity to 930 MW. Already, the Government has secured US$310 million from the Export-Import Bank of India for the exercise.

The rehabilitation will be done in phases.

The Government contracted Sino-Hydro to fund the expansion of Hwange in a deal worth US$1,2 billion.

On the power supply situation, Minister Soda said the power utility successfully negotiated for additional imports from EDM of Mozambique for 100 MW and 200 MW from Eskom of South Africa through the Southern Africa Power Pool.

ZESA also ramped up production at Hwange thermal plant and after bringing online two more units. The plant is currently producing an average of 440 megawatts.

There was also an improvement of power supplies from mini-hydro plant due to improved rains received so far.

In a related development, Green Fuel recently started supplying 8MW onto the grid from power generated at the ethanol production plant.

“We are hoping to get more water allocation for Kariba hydroelectric plant after the review of the hydrological situation at Kariba Dam on 15 January,” said Minister Soda.

Late last year, the Zambezi River Authority (ZRA), which manages Kariba Dam, ordered ZESA to stop production at the Kariba Hydroelectric Plant because of low usable water levels.

Kariba is the country’s largest power plant, with the capacity of producing 1 050 MW and has been the most reliable energy source. Hwange thermal plant, the country’s second-largest plant has become so unreliable because most of its equipment is obsolete. – The Herald

Tags: Energy and Power Development Minister Zhemu SodaGreen FuelHwange Thermal Power PlantHwange Unit 7
Share197Tweet123Share49
tendaik1

tendaik1

  • Trending
  • Comments
  • Latest
Richarlison World Cup goal voted best of the tournament

Richarlison World Cup goal voted best of the tournament

December 24, 2022
By-election victories have primed us for 2023 polls, says ZANU PF

By-election victories have primed us for 2023 polls, says ZANU PF

October 24, 2022
A new ocean is being formed in Africa

A new ocean is being formed in Africa

February 11, 2023
China in Africa: Who is fooling who?

China in Africa: Who is fooling who?

0
Zim/Iran seek improved economic relations

Zim/Iran seek improved economic relations

0
President Masisi to open Harare Agric show

President Masisi to open Harare Agric show

0
China in Africa: Who is fooling who?

China in Africa: Who is fooling who?

October 5, 2024
Sino-Zim: Turning the ironclad pact into dollars

Sino-Zim: Turning the ironclad pact into dollars

October 5, 2024
If our friends in China did it…

If our friends in China did it…

October 5, 2024
Zim Sentry

Copyright © 2022 ZimSentry. All Rights Reserved

Your Trusted Watchman

  • About
  • Advertise
  • Privacy & Policy
  • Contact

Follow Us

No Result
View All Result
  • Local News
  • Africa
  • International
  • Thought Leader
  • Economy
  • Lifestyle
  • Sports

Copyright © 2022 ZimSentry. All Rights Reserved

Welcome Back!

Login to your account below

Forgotten Password?

Create New Account!

Fill the forms below to register

All fields are required. Log In

Retrieve your password

Please enter your username or email address to reset your password.

Log In

You cannot copy content of this page